試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

After reviewing the monthly project performance report, the project manager, when monitoring & controlling risks, identifies the need to implement a contingency plan. What does the project manager need to do?
A、Change the project work breakdown structure to accommodate the implementation of the contingency plan.
B、Raise a change request to the project.
C、Re-baseline the project so that the contingency plan can be executed.
D、Raise an issue and escalate to the senior manager.